NEC Adoption by State

The National Electrical Code is adopted state by state, and in some states jurisdiction by jurisdiction, so the enforceable edition depends on where the work is. This table reconciles the major adoption trackers as of July 6, 2026: 7 states on NEC 2026 · 35 states on NEC 2023 · 6 states on NEC 2020 · 1 state on NEC 2017 · 1 state on NEC 2014 · 1 state on State-specific code (see note).

7

NEC 2026

35

NEC 2023

6

NEC 2020

1

NEC 2017

1

NEC 2014

1

State-specific code (see note)

NEC 2026

State Adoption Effective
Colorado Statewide adoption -
Idaho Statewide adoption -
Massachusetts Statewide adoption with state amendments -
New Hampshire Statewide adoption with state amendments -
Utah Statewide adoption with state amendments -
Vermont Statewide adoption with state amendments -
Washington Statewide adoption with state amendments -

NEC 2023

State Adoption Effective
Alabama Split/state-specific code (see note) -
Arizona Local adoption (varies by jurisdiction) -
Arkansas Statewide adoption with state amendments -
California Statewide adoption with state amendments January 1, 2026
Delaware Statewide adoption January 1, 2026
Florida Statewide adoption with state amendments -
Georgia Statewide adoption with state amendments -
Hawaii Statewide adoption -
Illinois Local adoption (varies by jurisdiction) -
Iowa Statewide adoption with state amendments July 1, 2025
Kansas Local adoption (varies by jurisdiction) -
Kentucky Statewide adoption January 1, 2025
Louisiana Statewide adoption -
Maine Statewide adoption July 1, 2024
Maryland Statewide adoption -
Michigan Statewide adoption with state amendments March 12, 2024
Minnesota Statewide adoption July 1, 2023
Mississippi Statewide adoption -
Missouri Local adoption (varies by jurisdiction) -
Nebraska Statewide adoption with state amendments August 1, 2024
Nevada Local adoption (varies by jurisdiction) -
New Jersey Statewide adoption with state amendments -
New Mexico Statewide adoption with state amendments -
New York Statewide adoption with state amendments December 31, 2025
North Dakota Statewide adoption July 1, 2024
Ohio Statewide adoption with state amendments March 1, 2024
Oklahoma Statewide adoption September 14, 2024
Oregon Statewide adoption with state amendments October 1, 2023 (NEC 2026 adopted, effective October 1, 2026)
Rhode Island Statewide adoption with state amendments December 1, 2025
South Carolina Statewide adoption with state amendments -
South Dakota Statewide adoption with state amendments November 12, 2024
Tennessee Statewide adoption with state amendments April 17, 2025
Texas Statewide adoption September 1, 2023
West Virginia Statewide adoption with state amendments -
Wyoming Statewide adoption July 1, 2023

NEC 2020

State Adoption Effective
Alaska Statewide adoption April 16, 2020
Connecticut Statewide adoption with state amendments October 1, 2022
Montana Statewide adoption with state amendments June 10, 2022
North Carolina Statewide adoption with state amendments November 1, 2021
Pennsylvania Statewide adoption -
Virginia Statewide adoption January 18, 2024

NEC 2017

State Adoption Effective
Wisconsin Statewide adoption August 1, 2018

NEC 2014

State Adoption Effective
District of Columbia Statewide adoption with state amendments May 29, 2020

State-specific code (see note)

State Adoption Effective
Indiana Split/state-specific code (see note) -

How to read this table

"Statewide" means a state agency adopts the National Electrical Code as a minimum for all (or most) occupancies; "with state amendments" means the state modifies the model code before adopting it. In local-adoption states there is no statewide electrical code, and each city or county picks its own edition. In every case the authority having jurisdiction issuing the permit determines the enforceable code. Statewide adoption does not prevent local amendments, and adoption dates shift on each state's rulemaking cycle. Click through to any state for edition details, effective dates, and verification notes.

Sources and methodology

Editions were reconciled across NFPA-derived adoption trackers current through March 2026, cross-checked against Mike Holt's adoption list, Faraday's 2026 state guide, JadeLearning's adoption table, and, where trackers conflicted, state rulemaking records. Effective dates appear only where a source stated one explicitly. Data is reviewed on a recurring schedule; the as-of date above reflects the last review.

Results are for reference only. Verify against the applicable adopted edition of the NEC and consult a licensed electrician for code compliance.