Separate Structure Grounding & Bonding Calculator
When a feeder or branch circuit leaves one building and lands in another, the National Electrical Code (NEC) 250.32 governs how to ground and bond the separate structure. Pick the supply type and whether the wiring is new or existing, and this tool tells you whether the structure needs its own grounding electrode, whether an equipment grounding conductor must be run with the supply, and whether the grounded (neutral) conductor is isolated at the structure or may serve as the bonding means.
How to use this calculator
- Pick what supplies the separate structure: a feeder (the usual subpanel case), a single branch circuit (a multiwire branch circuit counts as one), or more than one branch circuit.
- Say whether the wiring is a new installation or existing premises wiring.
- Optionally say whether an equipment grounding conductor is run with the supply.
- For existing wiring with no equipment grounding conductor, answer the two exception questions (metallic paths between the structures, and supply-side ground-fault protection).
- Read the result: the grounding electrode requirement, the equipment grounding conductor requirement, how to treat the neutral, and a compliance verdict.
NEC reference
This calculator implements NEC 2020 250.32, Buildings or Structures Supplied by a Feeder(s) or Branch Circuit(s). Section 250.32(A) requires a grounding electrode at the structure, with an exception for a single branch circuit that includes an equipment grounding conductor. Section 250.32(B)(1) requires an equipment grounding conductor to be run with the supply and the grounded conductor to be kept isolated at the structure. The 250.32(B)(1) Exception permits the grounded conductor to serve as the bonding and grounding means for existing premises wiring only, under three conditions. NEC 2020 is the site default; these provisions are substantially unchanged across the 2017, 2020, and 2023 editions, and the watershed was the 2008 edition, which ended the grounded-conductor method for new work.
Results are for reference only. Verify against the applicable adopted edition of the NEC and consult a licensed electrician for code compliance.
The three questions 250.32 answers
Feeding a detached garage, shop, barn, or well house raises the same three questions every time. 250.32 answers each one, and the answers depend on the supply type and whether the wiring is new or existing.
| Question | Rule | Source |
|---|---|---|
| Grounding electrode at the structure? | Required for a feeder or multiple branch circuits; waived only for a single branch circuit that carries an EGC | 250.32(A) |
| Equipment grounding conductor with the supply? | Required for all new work, sized per 250.122 | 250.32(B)(1) |
| Neutral bonded at the structure? | No for new work (isolate it); yes only under the existing-wiring exception | 250.32(B)(1) + Exception |
Why the neutral is isolated at a subpanel
The grounded (neutral) conductor and the equipment grounding conductor are bonded together at exactly one place in a grounded system: the service. If the neutral is bonded to the enclosure and ground again at a detached structure, normal neutral current divides between the neutral conductor and every parallel path back to the service, including the equipment grounding conductor, any metal conduit, and metal piping. That puts current on metal that is supposed to be dead and defeats the purpose of the grounding system. That is why 250.32(B)(1) requires a separate equipment grounding conductor with the feeder and the neutral floated at the structure: the neutral bar is isolated from the enclosure, and a separate ground bar is bonded to the enclosure and the grounding electrode.
The existing-wiring exception, in full
Before the 2008 NEC, a three-wire feeder (two hots and a neutral, no separate ground) to a detached structure was common, and the neutral was bonded at the structure with a local ground rod. The 2008 edition ended that for new work. The 250.32(B)(1) Exception keeps it legal for existing premises wiring only, and only when all three of these are true at once:
- No equipment grounding conductor is run with the supply to the structure.
- There are no continuous metallic paths bonded to the grounding system in both structures (no shared metal water line, no continuous metal conduit between them, and so on).
- No ground-fault protection of equipment is installed on the supply side of the feeder.
If any one fails, the grounded-conductor method is off the table and an equipment grounding conductor must be run with the neutral isolated. Where the grounded conductor is used for grounding under this exception, it is sized no smaller than the larger of 220.61 (neutral load) or 250.122 (equipment grounding conductor).
Worked examples
A new feeder runs to a 60 A subpanel in a detached garage. Because it is a feeder, the garage needs its own grounding electrode (250.32(A)). Because it is new work, a wire-type equipment grounding conductor is run with the feeder and sized per 250.122, and the neutral is isolated in the garage panel: no main bonding jumper, neutral bar floated, equipment grounds on a separate bonded ground bar (250.32(B)(1)). That installation complies.
A single 20 A multiwire branch circuit feeds a shed, run in cable with an equipment grounding conductor. Because only a single branch circuit supplies the shed and it carries an EGC, no grounding electrode is required at the shed (250.32(A) Exception), and the equipment grounds land on the circuit's EGC.
An existing barn is fed by an old three-wire feeder with the neutral bonded at the barn and a local ground rod. There is no metallic path between the house and barn and no supply-side ground-fault protection. Under the 250.32(B)(1) Exception for existing premises wiring, that arrangement is permitted to remain. Add a metal water line between the two buildings, though, and the exception no longer applies: the feeder must be upgraded to carry an equipment grounding conductor with the neutral isolated.
Common mistakes
- Bonding the neutral at a new detached subpanel. New work isolates the neutral at the structure; the main bonding jumper belongs at the service only.
- Skipping the ground rod at a feeder-fed structure. A feeder (or multiple branch circuits) always requires a grounding electrode at the structure.
- Reusing the old three-wire method on new work. The grounded-conductor method is an existing-wiring exception, not a choice for new installations.
- Missing a metallic path. A shared metal water line or continuous conduit between buildings voids the existing-wiring exception.
- Confusing a generator with a feeder. A generator at the structure is a separately derived system (250.30), not a 250.32 feeder case.
Frequently asked questions
Do I need a ground rod at a detached garage?
If it is fed by a feeder or more than one branch circuit, yes: 250.32(A) requires a grounding electrode at the structure. The only exception is a single branch circuit (multiwire counts as one) that already includes an equipment grounding conductor.
Do I bond neutral and ground in the detached subpanel?
Not for new work. Run an equipment grounding conductor with the feeder and keep the neutral isolated at the structure (250.32(B)(1)). Neutral and ground are bonded at the service only.
When is the old three-wire feeder still allowed?
Only for existing premises wiring, and only when no equipment grounding conductor is run, there are no metallic paths bonding the two grounding systems, and there is no supply-side ground-fault protection (250.32(B)(1) Exception).
How do I size the conductors?
The equipment grounding conductor is sized per Table 250.122 and the grounding electrode conductor per 250.66. This tool identifies which conductors are required; use the linked sizing calculators for the actual sizes.
Related calculators
- Equipment Grounding Conductor Size Calculator: size the EGC run with the feeder from the overcurrent device per NEC Table 250.122.
- Grounding Electrode Conductor Size Calculator: size the grounding electrode conductor at the structure per NEC Table 250.66.
- Neutral Load Calculator: the 220.61 neutral load used to size the grounded conductor under the existing-wiring exception.
- Ground Rod Resistance & Supplemental Rule Calculator: whether a single made electrode needs a supplemental electrode per NEC 250.53(A)(2).
Studying for the licensing exam? Our own NEC Code Quickstart works all twelve exam calculations start to finish, each with the code reference. Also in paperback. Going for the master license? NEC Master Electrician Exam Practice has 300 master-level questions with fully worked, table-cited answers, built on the 2023 NEC.
Running an electrical contracting business? Jobber handles scheduling, invoicing, and job management. Start a 14-day free trial.
Already have the software and the follow-up still is not happening? That is an unfilled seat rather than a missing tool. Our own Role Build covers the seat: three duties built to run start to finish inside the tools you already pay for.
For deeper NEC training on grounding and bonding, Mike Holt's NEC courses are the industry standard.
Working from the printed code? NEC code books and tab sets are available from Mike Holt.
This page contains affiliate links. ElectricalToolbox may earn a commission when you sign up or buy through them, at no additional cost to you.
Get new tools and reference cards by email
Occasional emails when a new calculator, guide, or printable card ships. No spam, unsubscribe anytime.